28.03.2016 - Carpentry Works

Carpentry Sketches after discussion with our ID






Carpentry Works in Progress

Kitchen Cabinets

Master Bedroom Wardrobe

Study Room in Progress







Thursday, March 17, 2016

Building Our Love Nest (Part 9)

(Week 3 - 14/03/2016 to 17/03/2016)

3D perspective out, Painting to be done, carpentry design

3D perspective finally out after so several chasings.




Not much shown for the study as the aluminium frames and glass doors will be done by another contactor.

14.03.2016 - Painting Starts
Colours Selection


Study Area

Dining Area


Master Bedroom

Bedroom 2

Living Room - Near Main Entrance


Living Room



Master Bedroom



Monday, March 7, 2016

Building Our Love Nest (Part 8)

Renovation Progress

Renovation Permit Obtained: 26.02.2016

(Week 1 - 29/02/2016 to 07/03/2016)

 Wet works and hacking being carried out.







(Week 2 - 08/03/2016 to 13/03/2016)

Making Good and fininshing touches on the wetworks. Electrical works also started.