Love Rain

Friday, April 15, 2016

Building our Love Nest - Final

Finally Renovation works are over. It was a new and exhausting experience for us but we survived through this. Now we are happy and proud owners of our new house.

Below are a few snippets of our house.



Living Room
TV Area


Kitchen


Study Area
Master Bedroom

Common Room


Master Room Toilet

Thursday, April 7, 2016

Building Our Love Nest (Part 12)

Finally after much waiting, the glassworks and aluminium works starts.

We got the following contractors to do the below works (not included in our ID package)

Glassworks (Shower Screen) : Ah Jia Glass (+65 9424 2332)
Aluminium Works (Glass panels and doors for the study room) - Nanhuat Contractor (Jiong Yang - +65 8428 1785)
Service Yard Window : A-Living Home Decor (Mr Gan +65 8692 4882)

Work In Progress




Completed Aluminium Works

Shower Screen (Master Bedroom)

Shower Screen (Common Toilet)


Overall i am quite satisfied with the workmanship and because i went direct, there was alot of cost savings.

Monday, April 4, 2016

Building Our Love Nest (Part 11)

04.04.2016 - Spot Check on the progress



Before Aluminium Works are up



Kitchen Carpentry



Common Room Wardrobe


Master Bedroom Wardrobe

Monday, March 28, 2016

Building Our Love Nest (Part 10)

28.03.2016 - Carpentry Works

Carpentry Sketches after discussion with our ID






Carpentry Works in Progress

Kitchen Cabinets

Master Bedroom Wardrobe

Study Room in Progress







Thursday, March 17, 2016

Building Our Love Nest (Part 9)

(Week 3 - 14/03/2016 to 17/03/2016)

3D perspective out, Painting to be done, carpentry design

3D perspective finally out after so several chasings.




Not much shown for the study as the aluminium frames and glass doors will be done by another contactor.

14.03.2016 - Painting Starts
Colours Selection


Study Area

Dining Area


Master Bedroom

Bedroom 2

Living Room - Near Main Entrance


Living Room



Master Bedroom



Monday, March 7, 2016

Building Our Love Nest (Part 8)

Renovation Progress

Renovation Permit Obtained: 26.02.2016

(Week 1 - 29/02/2016 to 07/03/2016)

 Wet works and hacking being carried out.







(Week 2 - 08/03/2016 to 13/03/2016)

Making Good and fininshing touches on the wetworks. Electrical works also started.